Educational University
Multiple Schools
Location:
Massachusetts
Owner:
Multiple School Districts
Service:
Construction Management
Contract Amount:
$71 Million (combined)

Served as the Construction Manager on the completion of a $71 million dollar, 6 site, defaulted project through out Massachusetts. Duties included ratification agreements, contracts, punch-list negotiations and work coordination with various subcontractors, as well as the communication, inspection, scheduling and payment requisitions with owner's representatives, architects and Town Boards. Projects included: Ambrose Elementary School, Worcester State College, Kathryn Stoklosa Middle School, Hillel House at Boston University, Olin College east Hall, and New Plympton Elementary School.